Status Update

March 12th, 2013:Beach fill operations for the Perdido Key segment, and the beach renourishment project as a whole, were completed today. The dredge Bayport has departed and demobilization efforts are underway. Beach tilling and grooming operations will occur in Gulf … Continue reading

Posted in Uncategorized |

WKRG – Rebuilding Baldwin Beaches (January 3, 2013)

Posted in Uncategorized |

Prior Updates

March 9th, 2013:Beach fill operations are approximately 75% complete on Perdido Key. Eastward fill operations are complete and the work is now progress westward toward the WindDrift Condominium and Gulf State Park (FL Point). March 7th 2013:Beach fill operations are … Continue reading