Project Status Updates
20 November 2024
U.S. Army Corps of Engineers (USACE), Jacksonville District, is preparing to continue beach renourishment operations for the Brevard County, Florida Shore Protection Project in the Mid-Reach segments between December 2024 and April 2025 (Season 2). The Mid-Reach project will be constructed with truck-haul sand owing to significant damage to the contractor’s dredge experienced in late October. Additionally, due to the dredge damage it is likely that the South Reach will be renourished in 2025/26 and not this year.
Areas along the northern Mid-Reach were partially filled during Season 1 (January-April 2024). These areas will be completed during Season 2 in addition to the areas along the southern Mid-Reach not renourished during Season 1.
Construction of the projects, contracted through The Dutra Group, began with renourishment of the Mid-Reach starting in March, 2024 but had to be paused at the end of April due to the start of sea turtle nesting season in Brevard County. During this time, roughly 102,000 cubic yards of sand were placed along the Mid-Reach between the southern border of Patrick Space Force Base and just south of Palm Springs Blvd in Indian Harbour Beach, Florida.
All work on the Mid-Reach beach is expected to be completed by April 30, 2025.
The USACE led project is 100% Federally funded with emergency funds in response to Hurricanes Ian and Nicole and is executed in partnership with the non-Federal sponsor, Brevard County Natural Resources Management Department, and their coastal engineering consultant Foth|Olsen.
An updated progress and schedule map is provided below.
The areas are clickable and list the approximate dates of work along that area. Dates are projected subject to change.