9 April 2025
The current work area is located in Segment 2 between approximately 3rd Street S and 6th Street S. Work along Segment 2 has been completed between the north end of the Segment 2 to 3rd Street S. Sand placement along Segment 1 was completed on 21-March-2025 and beach tilling along this segment was completed on 2-April-2025.
2 April 2025
The current work area is located in Segment 2 between approximately N 1st Street and 1st Street S. Sand placement along Segment 1 was completed on 21-March-2025 and beach tilling along this segment was completed on 2-April-2025.
27 March 2025
The current work area is located at the northern end of Segment 2 between approximately N 2nd Street and N 1st Street. Work along Segment 1 was completed on 21-March-2025.
Beach tilling will be conducted along the completed Segment 1 shoreline beginning on 31-March-2025 and will be conducted in the evenings when the beach is mostly unpopulated. Tilling is expected to be conducted from the jetty to north of the pier between 31-March to 2-April and from south of the pier to Shepard Park beginning on 2-April. Tilling is required by the project’s permits to “loosen up” the sand after the dredged fill placement for marine turtle nesting this summer.
19 March 2025
The current work area is located between approximately East Gadsden Lane and Palm Lane. Work has been completed between the north end of the project and East Gadsden Lane.
12 March 2025
The current work area is located between approximately East Leon Lane and East Gadsden Lane. Work has been completed between the north end of the project to East Leon Lane.
5 March 2025
The current work area is located between approximately Pulsipher Avenue and East Leon Lane. Work has been completed between the north end of the project to Pulsipher Avenue.
26 February 2025
The current work area is located between approximately Arthur Avenue and Taft Avenue. Work has been completed between the north end of the project and Arthur Avenue.
19 February 2025
The current work area is located between approximately Taylor Avenue and Johnson Avenue. Work has been completed between the north end of the project to Taylor Avenue.
13 February 2025
The current work area is located between approximately Monroe Avenue and Filmore Avenue. Work has been completed between the north end of the project to Monroe Avenue. The dredging contractor is thus far making rapid progress and anticipates being back on their target schedule within the next week or two (see progress map). Barring adverse seas or other delays, it is expected that the beach fill will reach the Cocoa Beach pier by about February 20 and then continue southward of the pier after February 21.
5 February 2025
The current work area is located between approximately E Central Blvd and Washington Avenue.
26 January 2025
Construction of the Bypass Project began on January 26, 2025 along the northernmost section of Segment 1.
Phase V Project Archive (2019)