Schedule

ALL DATES SUBJECT TO CHANGE

Schedule updated on September 14, 2016

Please call the Town of Longboat Key Public Works Department with schedule questions: 941-316-1988

 

Central Key Beach Renourishment Project

Truck Haul Beach Nourishment Project

Segment 1 Aria to Seaplace (North),

truck access from The Colony

(work area includes truck access corridor from The Colony through Seaplace to Aria)

Start: Week of April 4th, 2016
Finish: COMPLETED Week of April 25th, 2016
   
Segment 2 Westchester to Casa del Mar

truck access from Atlas Street

Start: Week of May 2nd, 2016
Finish: COMPLETED Week of May 16th, 2016
   
Segment 3 Gulfshore to Pelican Harbour (approx.)

truck access from Gulfshore/Buttonwood Cove

Start: Week of May 16th, 2016
Finish: COMPLETED Week of June 13th, 2016
   
Segment 4 Buttonwood Cove to Beachcomber (north, approx..)

truck access from Gulfshore/Buttonwood Cove, 3175 GMD, 2825 GMD

Start: Week of June 13th, 2016
Finish: COMPLETED Week of July 11th, 2016

Note: This schedule is based upon a minimum daily progress rate by the Contractor. Progress may be different than what is projected here. Updates will be provided as work progresses.

 

South End/New Pass Beach Nourishment Project

Hydraulic Dredging and Beach Disposal from New Pass

PROJECT L’Ambiance to Regent Place (approx.)
 Start: Week of August 15th, 2016
 Finish: Week of September 19th, 2016

 

North End/Longboat Pass Beach Nourishment Project

Hydraulic Dredging and Beach Disposal from Longboat Pass

PROJECT North Shore Road to Gulfside Road (two segments)
 Start: Week of September 19th, 2016
 Finish: Week of October 17th, 2016

 

Soutn End Emergency Truck Haul Beach Nourishment Project

Truck Haul Beach Nourishment Project

PROJECT Truck Haul placement at Longboat Key Club
Start: Week of September 19th, 2016
Finish: On or before the Week of October 17th, 2016

All dates and positions are approximate.

Legend 15Jul16-lr