Schedule
ALL DATES SUBJECT TO CHANGE
Schedule updated on September 14, 2016
Please call the Town of Longboat Key Public Works Department with schedule questions: 941-316-1988
Central Key Beach Renourishment Project
Truck Haul Beach Nourishment Project
Segment 1 | Aria to Seaplace (North),
truck access from The Colony (work area includes truck access corridor from The Colony through Seaplace to Aria) |
Start: | Week of April 4th, 2016 |
Finish: | COMPLETED Week of April 25th, 2016 |
Segment 2 | Westchester to Casa del Mar
truck access from Atlas Street |
Start: | Week of May 2nd, 2016 |
Finish: | COMPLETED Week of May 16th, 2016 |
Segment 3 | Gulfshore to Pelican Harbour (approx.)
truck access from Gulfshore/Buttonwood Cove |
Start: | Week of May 16th, 2016 |
Finish: | COMPLETED Week of June 13th, 2016 |
Segment 4 | Buttonwood Cove to Beachcomber (north, approx..)
truck access from Gulfshore/Buttonwood Cove, 3175 GMD, 2825 GMD |
Start: | Week of June 13th, 2016 |
Finish: | COMPLETED Week of July 11th, 2016 |
Note: This schedule is based upon a minimum daily progress rate by the Contractor. Progress may be different than what is projected here. Updates will be provided as work progresses.
South End/New Pass Beach Nourishment Project
Hydraulic Dredging and Beach Disposal from New Pass
PROJECT | L’Ambiance to Regent Place (approx.) |
Start: | Week of August 15th, 2016 |
Finish: | Week of September 19th, 2016 |
North End/Longboat Pass Beach Nourishment Project
Hydraulic Dredging and Beach Disposal from Longboat Pass
PROJECT | North Shore Road to Gulfside Road (two segments) |
Start: | Week of September 19th, 2016 |
Finish: | Week of October 17th, 2016 |
Soutn End Emergency Truck Haul Beach Nourishment Project
Truck Haul Beach Nourishment Project
PROJECT | Truck Haul placement at Longboat Key Club |
Start: | Week of September 19th, 2016 |
Finish: | On or before the Week of October 17th, 2016 |
All dates and positions are approximate.