Project Status Update
DATE: February 2022
The project is complete.
Beach fill operations were completed in mid-January 2022, and the Contractor’s demobilization process was completed by mid-February 2022. Likewise, post-construction monitoring surveys were conducted during that time.
Future activities will consist of monitoring for sea turtle nesting, shorebird activity, and the physical performance of the beach nourishment project. The next survey of the beach will occur this Summer (July 2022, est.), with annual beach monitoring surveys to occur thereafter in accordance
Please see the Google Map below for the location of the various work segments
Please visit the PHOTOS tab above for construction progress images, and see the Frequently Asked Questions (FAQ) tab at the top of this page for additional information.